Benchmarks · measured 31 July 2026
We reconstruct project records from published judgments - Wembley Stadium, The Shard, FIDIC works, offshore fabrication - and run them through the engine. The court's own findings of fact are the answer key: a chronology nobody at datum authored. Every number below comes from the engine's own scorecard against committed truth files.
| Case | Record | Document dating | Event recall | |
|---|---|---|---|---|
| Walter Lilly v MackayWalter Lilly & Co v Mackay [2012] EWHC 1773 (TCC)The landmark London EOT judgment: full extension of time to practical completion. datum also drafted and exported the claim - 26 of 26 factual sentences carried verified citations. | 16 docs | 100% | 11/11 · 100% | |
| Multiplex v HoneywellMultiplex v Honeywell (No. 2) [2007] EWHC 447 (TCC)Wembley Stadium: revised programmes as acts of prevention; the time-at-large argument dismissed. | 12 docs | 100% | 12/12 · 100% | |
| De Beers v AtosDe Beers UK v Atos Origin [2010] EWHC 3276 (TCC)A delayed IT programme, not a building site - the same method reads any dated project record. | 14 docs | 100% | 11/12 · 92% | |
| Obrascon v GibraltarObrascon Huarte Lain v AG for Gibraltar [2014] EWHC 1028 (TCC)FIDIC Yellow Book - the Gulf's contract family. Clause 20.1 notice timing decided the claim. | 14 docs | 100% | 11/12 · 92% | |
| Bluewater v MerconBluewater v Mercon [2014] EWHC 2132 (TCC)Offshore fabrication: milestones, variation orders, notice of default, termination. | 14 docs | 100% | 11/12 · 92% | |
| Thomas Barnes v BlackburnThomas Barnes v Blackburn with Darwen BC [2022] EWHC 2598 (TCC)Modern concurrent-delay analysis: employer-risk steel remedials against contractor-risk roof delay. | 14 docs | 100% | 11/12 · 92% | |
| Costain v HaswellCostain v Charles Haswell [2009] EWHC 3140 (TCC)A critical-path fight over piled foundations - which delay actually drove completion. | 13 docs | 100% | 10/12 · 83% | |
| Cleveland Bridge v SeverfieldCleveland Bridge v Severfield-Rowen [2012] EWHC 3652 (TCC)Steelwork for The Shard: 42 days of culpable fabrication delay found against the subcontractor. | 14 docs | 100% | 10/12 · 83% | |
| Adyard v SD MarineAdyard Abu Dhabi v SD Marine [2011] EWHC 848 (Comm)An Abu Dhabi shipyard: the prevention principle and concurrency under English law.Regulatory correspondence - events are positions stated inside long letters. | 14 docs | 100% | 8/12 · 67% | |
| Van Oord v AllseasVan Oord v Allseas [2015] EWHC 3074 (TCC)A GBP 10m disruption claim dismissed for poor substantiation - the cautionary tale datum exists to prevent.Claim letters recounting months of history - many events buried per document. | 14 docs | 100% | 8/12 · 67% | |
| Fluor v SZHIFluor v Shanghai Zhenhua [2016] EWHC 2062 (TCC)Offshore wind foundations: weld cracking, NCR chains and re-inspection campaigns.Dense NCR documents carrying several dated facts each - the hardest extraction shape. | 14 docs | 100% | 9/12 · 75% |
Also in the harness: 96 offline tests on real services in CI, a deterministic CPM engine verified against textbook schedules, and a citation gate that blocks export of any unproven sentence. These corpora are rehearsal assets: real-shaped, with adjudicated ground truth we did not write. They complement - never replace - pilot validation on a genuinely real claim record with a practitioner's review.
Want the engine graded on your own record? That is exactly what a pilot is.
Request a pilot